Certify an End-Stage Renal Disease Facility
Purpose: This procedure briefly describes the steps to establish a certified end-stage renal disease facility in North Carolina. The federal requirements can be found in the Code of Federal Regulations at 42 CFR 405.2102-405.2180 (PDF, 1.63 MB).
Because individual projects may have special circumstances, there may be variations in the process that are not covered in these setps. The outline is intended to be a general guide to aid the applicant in completing the overall project.
Contacts: For questions regarding any part of the process, please contact the appropriate sections of the N.C. Division of Health Service Regulation:
Procedure Summary:
In order to establish an end-stage renal disease facility in North Carolina, an applicant must first review the State Medical Facilities Plan. Applicants must obtain a certificate of need, and then apply for Medicare/Medicaid certification.
Procedures:
- Review the State Medical Facilities Plan: Healthcare Planning
- Applicants can learn about the methodology for determining the need to establish a dialysis facility by reviewing the State Medical Facilities Plan, which is published each calendar year. The Plan also specifies the number of additional dialysis stations needed on a county and facility basis.
- Applicants can also find the Certificate of Need review schedules and deadline for submittal of applications to establish a dialysis facility in the Semiannual Dialysis Reports. No one may develop a dialysis facility without first obtaining a certificate of need.
- Obtain a Certificate of Need: Certificate of Need (CON)
- The applicant submits an application for the proposed dialysis facility to CON for review and approval according to the schedule outlined in the State Medical Facilities. If the applicant is leasing the facility, both the prospective owner/lessor and the lessee of the facility must submit a joint application.
- CON advertises a written public comment period. Within 30 days of the beginning of the review period, written comments may be filed by any person regarding the proposals under review, although an applicant may not comment on its own proposal.
- CON may conduct a public hearing within 30 to 50 days from the beginning of the review period, at which time the applicant is given the opportunity to respond to written comments submitted to CON and inquiries made at the hearing.
- CON decides to approve or disapprove an application within 150 days of the beginning of the review period.
- CON issues a certificate of need 35 days after the date of approval if a petition for a contested case hearing is not filed.
- After a certificate of need is issued, the applicant contacts the Acute and Home Care Licensure and Certification Section about the requirements for the development of dialysis stations.
- Obtain Certification: Acute and Home Care Licensure and Certification Section
- At least three months before operation, the facility contacts the section for an application packet. The applicant completes and returns all forms to the section.
- The section forwards the Medicare Provider Enrollment Application to the fiscal intermediary to approve or disapprove.
- The initial survey is scheduled within three weeks of the notice of the fiscal intermediary’s approval.
- If a facility has deficiencies during the initial survey, the effective date of certification will be the latest date that an acceptable Plan of Correction is signed by the facility.
- The section forwards all information to the Dallas Centers for Medicare & Medicaid Services (CMS) Regional Office for approval.
- The regional office assigns the CMS Certification Number (CCN) and notifies the fiscal intermediary.